Srinagar: The Kashmir Power Distribution Corporation Limited (KPDCL) has announced a series of scheduled power shutdowns to facilitate essential maintenance and repair work on several high-tension transmission lines and grid stations. The most significant disruption is set to begin on Saturday, January 17, involving the Delina Grid Sub-Station, which will impact electricity supply across large parts of North and Central Kashmir for a week.
Week-Long Outage: Delina GSS Schedule (Jan 17 – Jan 23)
According to the Chief Engineer, Distribution (KPDCL), a daily two-hour shutdown will be observed at the 480 MVA 220/132/33 kV Grid Sub-Station Delina from 11:00 AM to 1:00 PM starting tomorrow.
Affected Areas Include:
- Baramulla & Surroundings: Panzipora, Tarzoo, Hygam, Shair Colony, Arampora, Mahrajpora, Bugoo, Hathlangoo, Warpora, Dooru, Shiva, Tujjar Sharief, Shrian, Nowpora, Mazbugh, and Reban.
- Central & North Localities: Achabal, Doabgah, Ferozpora, Panzulla, Shutloo, Chakloo, Ladoora, Nadihal, Seer, and Dangiwachi.
- Critical Installations: DC Office Baramulla, Fruit Mandi, Railway installations, Water Supply Schemes, and Industrial units.
Additional Scheduled Interruptions (Jan 17 – Jan 21)
In addition to the Delina GSS, several other 33 kV lines will undergo maintenance:
- Ganderbal (Wangath Tap Line): Power supply to Babanagri, Wangath, Naranag, and Kachnambal will remain affected on January 17 from 9:30 AM to 3:00 PM.
- South Kashmir (Wanpoh SICOP Line): Disruptions scheduled for January 19 and 21 (10:00 AM to 3:00 PM) in Veer, Srigufwara, Zirpara, and Bijbehara areas.
- Ganderbal (Lar Tap Line): Outages expected on January 19 (10:00 AM to 3:00 PM) for Lar, Waliwar, and Repore.
Key Highlights Box:
- Major Shutdown: Delina GSS (North/Central Kashmir).
- Duration: Jan 17 to Jan 23 (11:00 AM – 1:00 PM daily).
- Reason: Essential maintenance and system reliability upgrades.
- Emergency Support: Residents are advised to keep devices charged and verify local schedules with their nearest electric division.
FAQ Section:
A1: KPDCL states that these maintenance works are critical to prevent unscheduled breakdowns and to stabilize the grid during the peak load period of Chillai Kalan.
A2: KPDCL aims to strictly adhere to the 11 AM – 1 PM window, though minor delays may occur depending on the progress of the technical work.
Read Also:
AUTHORSHIP & TRANSPARENCY
- Sign-off: Reported by KittoNews Desk | Edited by Senior Editor Gowhar Nabi.
- Source Transparency: Information is based on official communiqués from the Chief Engineer, Distribution, KPDCL issued on Jan 15-16, 2026.
- Disclaimer: Power schedules are subject to weather conditions. Extreme snowfall or emergencies may lead to the cancellation or rescheduling of these shutdowns.
- Community Question: Is your area facing unscheduled power cuts despite the official schedule? Let us know in the comments.
- Accountability Footer: Found an error or have a news tip? Email kittonews@gmail.com.